BHP says it is working to bring its Jansen potash mine into operation sooner than expected.

The company says it is working to bring forward Stage 1 first production at the Saskatchewan mine to 2026.

When BHP announced last year that it was going ahead with the project, the company said it wouldn’t come into operation until 2027.

However, in an operational review released Tuesday, the company says the project is tracking to plan and it is working to begin production ahead of its initial schedule.

BHP also says it is assessing options to accelerate the second stage of the project.

The Jansen mine, located about 140 kilometres east of Saskatoon, is expected to produce about 4.35 million tonnes of potash per year with the potential for further expansions.

Be smart with your money. Get the latest investing insights delivered right to your inbox three times a week, with the Globe Investor newsletter. Sign up today.

Follow related authors and topics

Authors and topics you follow will be added to your personal news feed in Following.

Interact with The Globe